Wells of Titas Gas Field

Well No.

Spud-in Date

Completion Date

Well Type

Drilled Depth (ft)

Production String

Production Casing

Perforated Interval (ft)

Completion Zone (Sand)

Present Status

           Titas Gas Field

1

1st June-1962

1st Nov-1962

Vertical

12325

41/2 //

95/8//

8586-9085

A

Flowing

2

22nd Nov.-1962

6th Jan-1963

Vertical

10574

41/2 //

7//

8614-9030

A

Flowing

3

3rd Aug.-1969

8th Sep-1969

Vertical

9315

41/2 //

7//

8589-9186

A

Plagged & Abandoned

4

14th Sep.-1969

30th Oct-1969

Vertical

9350

41/2 //

7//

8632-9188

A

Flowing

5

5th Oct.-1980

6th Jan-1981

Directional

10805

41/2 //

7//

9585-10014

A

Flowing

6

7th May-1983

11th Oct-1983

Vertical

10072

41/2 //

7//

8648-8976

A

Flowing

7

1st Dec.-1984

17th Mar,1985

Directional

11006

41/2 //

7//

10082-10674

A

Flowing

8

25th May-1985

28th Sep-1985

Directional

11760

41/2 //

7//

10804-11651

A

Flowing

9

11th Sep.-1987

20th Jan-1988

Directional

11893

41/2 //

7//

10860-11713

B & C

Flowing

10

14th Feb.-1988

29th May-1988

Directional

12139

41/2 //

7//

11394-12063

B & C

Flowing

11

10th Feb.-1990

27th April-1990

Vertical

10462

31/2 //

7//

8700-8902

A

        Flowing

12

17th Jun-1999

22nd Aug.-1999

Directional

9873

41/2 //

95/8//

9091-9402

A

Flowing

13

27th Aug.-1999

2nd Dec-1999

Directional

11487

41/2 //

95/8// & 7//

10060-10276

A

Flowing

14

7th Dec.-1999

11th Mar-2000
Re-completion date : 11th Sept.- 2000

Directional

11004

41/2 //

95/8// & 7//

9299-9341

A

Flowing

15

3 Feb-2006

14 May-2006

Vertical

10446

41/2 //

95/8// & 7//

8885'-9121'

A

Flowing

16

7Aug-2005

17 Dec-2005

Directional

11673

41/2 //

95/8// & 7//

10020-10535

A

Flowing

17

31 Aug-2012

7 Feb-2013

Vertical

9424

41/2 //

95/8// & 7//

9026-9098

A

Flowing

18

19 March -2013

06 August -2013

Directional

10932

41/2 //

95/8// & 7//

10348-10686

A

Flowing

19

16 March -2014

20 May -2014

Directional

12730

41/2 //

95/8// & 7//

10507-10517
10548-10591
10671-10707

A

Flowing

20

27 February’ 2013

31 October -2013

Directional

11585

41/2 //

95/8// & 7//

10070-10106

A

Flowing

21

03 November’ 2013

30 December -2013

Directional

11631

41/2 //

95/8// & 7//

10282-10322
10477-10535
10653-10745

A

Flowing

22

16 January’ 2014

07 March -2014

Directional

11926

41/2 //

95/8// & 7//

11224-11248
11323-11343

A

Stand-by

25

27 December' 2015

27 March - 2016

Vertical

11680

41/2 //

7//

8840-9036

A

Flowing

26

02 February'2016

02 July-2016

Directional

12618

41/2 //

95/8// & 7//

12382-12441

c

Flowing

27

19 November’ 2014

11- April -2014

Directional

10292

41/2 //

95/8// & 7//

9649-9934

A

Flowing

 

 

 

Liaison Office:

Petrocentre (14th floor)
Petrobangla
3, Kawranbazar C/A, Dhaka-1215
Bangladesh
Tel : 88-02-8189508
Fax : 88-02-8189507
E-mail : This email address is being protected from spambots. You need JavaScript enabled to view it.

Head Office:

Birashar, Brahmanbaria.
Bangladesh

PABX - 88-0851-58141, 58428, 59128

Fax : 88-0851-59390, 58429, 58758

This email address is being protected from spambots. You need JavaScript enabled to view it.

http://www.bgfcl.org.bd/

Fields Of BGFCL:

 

 

 

 

 

 

 

Webmail

Total Visitors

3505